Oracle to Snowflake for investment banking payments

Data migrationFinancial servicesPayments analyticsData enablementBI modernization

Outcomes

What changed for the payments team

Automated reconciliation and validation to support controlled cutover

Consistent KPI definitions across payment rails and reporting teams

Faster reporting delivery through modern modelling standards and reusable datasets

Accelerated Oracle migration with a wave based plan, automated testing, and parallel runs for critical payment domains

Reduced reporting friction through a single set of definitions and a governed semantic layer

Improved reliability with monitoring, data quality checks, and a clear release process for pipelines and models

Challenge

Complex reporting, slow change

The payments function needed to modernize a reporting estate that had grown complex over time. Critical payment and event data was stored and reported from Oracle, with transformation logic spread across stored procedures, scheduled jobs, and manual steps.

Operational and control teams relied on similar reports with different definitions, which created rework and reduced trust. Change cycles were slow because reporting and transformation logic were tightly coupled, and validation was time consuming during month end and audit periods.

The team needed a migration approach that reduced risk, preserved auditability, and improved performance without interrupting daily operations.

Solution

A controlled, refactor first migration

Datasphere Dynamics delivered a controlled migration from Oracle to Snowflake with a refactor first approach.

We mapped the payments reporting landscape and grouped assets into migration waves based on business criticality and cutover risk. Automated reconciliation checks validated every migrated dataset for completeness and accuracy.

To modernize analytics, we rebuilt transformations using consistent modelling standards, embedded testing, and documentation, then delivered a governed BI layer with agreed KPI definitions to remove reporting inconsistency across teams.

Alongside the build, we introduced practical operating standards for quality, monitoring, and releases so the platform stayed reliable after cutover.

9

Months

Total project duration.

5

Dedicated team members

Full time resources on the programme.

Technology used

OracleAWS S3SnowflakedbtPower BI

Planning a similar migration?

We can assess your estate, group it into controlled waves, and give you a cutover plan your risk teams will sign off.